Under NERC reliability standards, what is the purpose of the 'N-1' contingency planning requirement?
-
A
Ensure the grid can withstand the loss of any single element without cascading failure
-
B
Mandate that utilities maintain one backup power plant at all times
-
C
Require one spare transmission line for every active line
-
D
Ensure renewable energy meets at least 1% of peak demand