Project Finance and Economics Flashcards

7 cards from real REP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Finance and Economics flashcards as text
  1. What is a 'financing gap' in the context of renewable energy project development, and what tool commonly bridges it?

    Answer: The shortfall between available senior debt and total project cost, often bridged by tax equity, mezzanine debt, or grants

    After senior debt is fully sized, any remaining funding gap is typically filled with tax equity, subordinated mezzanine loans, government grants, or additional sponsor equity.

  2. How does 'revenue quality' affect the cost of capital for a renewable energy project?

    Answer: Projects with higher-quality revenue (long-term PPAs with creditworthy offtakers) typically achieve lower interest rates and better financing terms

    A bankable, investment-grade PPA reduces lender risk, enabling more favorable debt terms (lower spreads, higher leverage), which lowers the weighted average cost of capital.

  3. What is the 'sculpted debt service' approach in renewable energy project finance?

    Answer: A repayment schedule where debt service payments vary each period to match projected cash flow, maintaining a target DSCR

    Sculpted debt service tailors principal payments to the project's cash flow profile (accounting for seasonal or degradation effects) to maintain a consistent DSCR throughout the loan term.

  4. Which of the following most accurately describes the Investment Tax Credit (ITC) for solar projects under current U.S. law?

    Answer: A one-time credit equal to a percentage of qualified capital costs, claimable in the year the project is placed in service

    The ITC (Section 48) provides a federal tax credit based on a percentage of eligible project capital costs, claimed in the tax year the system is placed in service.

  5. What is 'time-of-delivery' (TOD) pricing in a PPA, and why does it matter for project economics?

    Answer: A payment structure where the offtaker pays a premium for energy delivered during peak demand hours, increasing revenue during high-value periods

    TOD pricing multiplies the base PPA rate by factors that are higher during peak hours and lower off-peak, aligning project revenue with the grid's value of energy across the day.

  6. In project finance, what does 'cash flow waterfall' refer to?

    Answer: The sequential order in which operating revenues are allocated to expenses, reserves, debt service, and equity distributions

    The cash flow waterfall defines the priority of payments — typically: operating costs → senior debt service → reserve funding → subordinated debt → sponsor distributions — ensuring senior obligations are paid first.

  7. What is the purpose of a 'completion guarantee' in renewable energy project finance?

    Answer: It is a sponsor commitment to lenders to cover cost overruns and complete construction if the EPC contractor defaults

    A completion guarantee is a credit support instrument from the sponsor (or parent) that obligates them to fund construction completion if the contractor fails, protecting lenders' collateral.