Ramsay Test Time Management & Efficiency 2 — Questions and Answers
Question 1: You have four maintenance tasks due today but only enough time for three. What is the BEST first step?
- Prioritize by urgency and impact on production (Correct answer)
- Complete them in the order they were received
- Do the easiest task first to feel productive
- Wait for your supervisor to choose for you
Correct answer: Prioritize by urgency and impact on production
Ranking tasks by urgency and production impact ensures the most critical work gets done first.
Question 2: A technician finishes a job 20 minutes early. The most efficient use of that time is to:
- Begin preparing for the next scheduled task (Correct answer)
- Take an extra unscheduled break
- Redo finished work that was already correct
- Leave the area until the next shift
Correct answer: Begin preparing for the next scheduled task
Using spare time to prepare for upcoming work maximizes overall productivity.
Question 3: Which practice MOST reduces wasted time during a repair job?
- Gathering all needed tools and parts before starting (Correct answer)
- Searching for each tool as you need it
- Borrowing tools mid-task from coworkers
- Starting without checking what is required
Correct answer: Gathering all needed tools and parts before starting
Collecting tools and parts up front avoids repeated trips and interruptions.
Question 4: A machine runs three parts per minute. How many parts are produced in 15 minutes?
- 45 (Correct answer)
- 30
- 50
- 18
Correct answer: 45
3 parts × 15 minutes = 45 parts.
Question 5: When several urgent requests arrive at once, the efficient response is to:
- Quickly assess which has the greatest consequence if delayed (Correct answer)
- Handle whichever person asked most loudly
- Ignore all of them until things calm down
- Start all tasks at the same time
Correct answer: Quickly assess which has the greatest consequence if delayed
Evaluating consequences of delay helps order competing urgent tasks correctly.
Question 6: Keeping a clean, organized workspace primarily improves efficiency by:
- Reducing time spent searching for tools and materials (Correct answer)
- Impressing visitors to the facility
- Making the area look busier
- Allowing more items to be stored
Correct answer: Reducing time spent searching for tools and materials
An organized workspace minimizes search time and speeds up tasks.
Question 7: A scheduled task takes 2.5 hours. If you start at 8:00 AM, when will it finish?
- 10:30 AM (Correct answer)
- 10:00 AM
- 11:00 AM
- 9:30 AM
Correct answer: 10:30 AM
8:00 AM plus 2 hours 30 minutes equals 10:30 AM.