During an audit, an auditor discovers that a corrective action from a previous audit was implemented but is no longer effective. What is the most appropriate action?
-
A
Close the finding since the action was implemented
-
B
Document it as a new nonconformity and record it in the audit report
-
C
Ignore it because it falls outside the current audit scope
-
D
Ask management to re-implement the same corrective action