PSPO - Professional Scrum Product Owner Practice Test
PSPO Sprint Planning and Collaboration 2
What is the maximum length of a Sprint Planning event for a one-month Sprint?
Select your answer
A
2 hours
B
4 hours
C
8 hours
D
16 hours
Hint