A project manager is evaluating whether to deploy software updates during a major product launch. The risk of deployment failure during peak traffic is rated HIGH. The BEST response is to:
-
A
Deploy immediately to fix existing bugs
-
B
Defer the update until after the launch window using a change freeze
-
C
Transfer the risk to the DevOps team
-
D
Accept the risk without any adjustment