A project manager discovers that a third-party SaaS vendor will sunset the platform the project relies on mid-delivery. What is the BEST immediate risk response?
-
A
Ignore it until the vendor officially announces
-
B
Trigger a contingency plan to evaluate alternative platforms
-
C
Escalate to the sponsor and halt all work
-
D
Remove the dependency from the project scope