A project manager identifies that if a competitor releases a similar product early, it will invalidate the project's business case. The team decides to accelerate the project schedule to beat the competitor. This response strategy for an opportunity is:
-
A
Exploit
-
B
Enhance
-
C
Share
-
D
Accept