Project Risk Management Risk Response Strategies 2 — Questions and Answers
Question 1: A project team decides to purchase insurance to cover potential losses from a major equipment failure. Which risk response strategy does this represent?
- Avoid
- Transfer (Correct answer)
- Mitigate
- Accept
Correct answer: Transfer
Purchasing insurance transfers the financial impact of a risk to a third party (the insurer).
Question 2: Which of the following is the BEST example of a risk avoidance strategy?
- Adding a contingency reserve to the budget
- Eliminating a high-risk project phase from the scope (Correct answer)
- Outsourcing risky activities to a vendor
- Documenting the risk in the risk register
Correct answer: Eliminating a high-risk project phase from the scope
Avoidance eliminates the risk entirely, often by changing the project plan or removing the source of the risk.
Question 3: A risk response plan requires significant upfront investment but substantially reduces the probability of a critical risk. What should the project manager evaluate to justify this response?
- The risk's proximity on the schedule
- Whether the cost of the response is less than the expected monetary value of the risk (Correct answer)
- The number of stakeholders affected by the risk
- The risk owner's availability
Correct answer: Whether the cost of the response is less than the expected monetary value of the risk
A response is justified when its cost is less than the expected monetary value (probability × impact) of the risk it addresses.
Question 4: Passive acceptance of a risk means the project team will:
- Monitor the risk and implement a contingency plan if it occurs
- Take no action and deal with consequences if the risk occurs (Correct answer)
- Reduce the probability of the risk occurring
- Transfer the risk to a third party
Correct answer: Take no action and deal with consequences if the risk occurs
Passive acceptance involves no proactive action; the team simply deals with the risk if and when it materializes.
Question 5: A software project team identifies that a critical dependency on a vendor could delay the project. They negotiate a contractual penalty clause for late delivery. This is an example of:
- Exploit
- Transfer (Correct answer)
- Mitigate
- Enhance
Correct answer: Transfer
Shifting the financial consequence of the vendor's delay to the vendor via a penalty clause is a risk transfer strategy.
Question 6: Which risk response strategy is most appropriate for a threat that has very low probability and very low impact?
- Avoid
- Transfer
- Mitigate
- Accept (Correct answer)
Correct answer: Accept
Low-probability, low-impact threats are typically accepted because the cost of a response would exceed the expected loss.
Question 7: A risk response owner is assigned in the risk register. What is this person primarily responsible for?
- Approving the project budget contingency
- Implementing and monitoring the agreed risk response plan (Correct answer)
- Identifying new risks throughout the project
- Reporting risk status to the project sponsor
Correct answer: Implementing and monitoring the agreed risk response plan
The risk response owner is accountable for executing and monitoring the specific risk response strategy assigned to them.
A project team decides to purchase insurance to cover potential losses from a major equipment failure.
Which risk response strategy does this represent?