A project team identifies that their industry has significant regulatory risk. How should this influence the risk breakdown structure (RBS) in the risk management plan?
-
A
Regulatory risk should be excluded since it is outside the team's control
-
B
A regulatory risk category should be explicitly included in the RBS
-
C
The RBS should only include internal project risks
-
D
Regulatory risks are addressed only in the procurement management plan