A newly appointed project manager takes over a project that has no risk management plan. What should be the FIRST step?
-
A
Begin identifying risks immediately
-
B
Conduct Plan Risk Management to establish the approach before proceeding
-
C
Review the issue log for existing problems
-
D
Update the project schedule to include risk activities