A project team realizes that a key vendor's financial instability is a risk they nearly overlooked. Which risk identification approach would BEST help capture external supply chain risks systematically?
-
A
Internal brainstorming only
-
B
Environmental scanning and external stakeholder interviews
-
C
Reviewing only the project scope statement
-
D
Analyzing the team's communication plan