A project team sets a contingency reserve at the P70 level from simulation results. What risk remains unaddressed by this reserve?
-
A
The 30% of scenarios that exceed the P70 estimate
-
B
All identified risks not yet analyzed quantitatively
-
C
Risks with a probability below 10%
-
D
Secondary risks triggered by risk responses