A project team runs a Monte Carlo simulation and finds the P80 completion date is 6 weeks later than the deterministic schedule. What does P80 mean?
-
A
80% of simulated runs finished on or before that date
-
B
80% of risks have been identified and quantified
-
C
The schedule has an 80% confidence interval of ±6 weeks
-
D
80% of project costs fall within the estimated range