A project team is using the 'five whys' technique during a quality review. What is the PRIMARY goal of this technique?
-
A
To document five examples of the defect for the lessons learned register
-
B
To iteratively ask 'why' to drill down to the fundamental root cause of a problem
-
C
To identify five potential solutions for a quality deviation
-
D
To assign accountability for a quality failure across five team members