A Pareto chart reveals that 3 defect types account for 78% of all quality failures. What is the recommended project management response?
-
A
Address all defect types simultaneously to ensure comprehensive coverage
-
B
Focus corrective action on the 3 dominant defect types first
-
C
Discard the remaining defect types as insignificant
-
D
Escalate all defect types to the sponsor for prioritization