A project risk manager is leading a lessons-learned session after a major risk event. What is the PRIMARY professional purpose of this activity?
-
A
To assign blame for the risk materializing
-
B
To document insights that improve risk management on future projects
-
C
To justify the risk budget overrun to senior management
-
D
To close out the risk register without further action