What is the primary purpose of the contract closeout process in project risk management?
-
A
To renegotiate contract terms for similar future projects
-
B
To confirm deliverables are complete, payments settled, and lessons learned captured
-
C
To transfer remaining contract budget to other active project areas
-
D
To automatically extend warranty periods for all delivered goods