What is the primary purpose of resource leveling in project scheduling?
Select your answer
A
To ensure each team member receives equal compensation
B
To adjust activity start/end dates to resolve resource over-allocation, even if it extends the project
C
To match the project budget with resource cost requirements
D
To distribute project risks evenly across all team members