Project Management Project Scope and WBS 4 — Questions and Answers
Question 1: A WBS dictionary primarily serves to:
- Define the WBS numbering system
- Provide detailed descriptions of each WBS component including acceptance criteria (Correct answer)
- List all project stakeholders by role
- Summarize the project budget by phase
Correct answer: Provide detailed descriptions of each WBS component including acceptance criteria
The WBS dictionary supports each WBS component with details such as description, acceptance criteria, responsible party, and resource requirements.
Question 2: Scope creep most commonly results from:
- Poor risk management
- Inadequate change control and stakeholder management (Correct answer)
- Aggressive project scheduling
- Insufficient team training
Correct answer: Inadequate change control and stakeholder management
Scope creep typically occurs when changes are allowed informally without going through change control and stakeholder agreements are unclear.
Question 3: On a large program, a project manager is uncertain about the details of work that is 6 months away. The best approach is:
- Delay planning until the work is closer
- Use rolling wave planning to plan near-term work in detail and far-term work at a high level (Correct answer)
- Define all work packages now to avoid future rework
- Create a separate project for the future work
Correct answer: Use rolling wave planning to plan near-term work in detail and far-term work at a high level
Rolling wave planning allows progressive elaboration, detailing near-term work while keeping far-term work at a higher level until more information is available.
Question 4: Which of the following is NOT typically included in a project scope statement?
- Project deliverables
- Project exclusions
- Resource assignments by name (Correct answer)
- Acceptance criteria
Correct answer: Resource assignments by name
Resource assignments by name belong in the resource management plan, not the scope statement.
Question 5: A customer requests a feature during execution that was explicitly listed as an exclusion in the scope statement. The PM should:
- Add it immediately to maintain the relationship
- Evaluate the request and process it through integrated change control (Correct answer)
- Refuse the request without evaluation since it was excluded
- Add it to the backlog for the next project phase
Correct answer: Evaluate the request and process it through integrated change control
Even excluded items can be added via formal change control; the PM should evaluate and process the request properly rather than refusing outright.
Question 6: The process of monitoring the status of the project and product scope and managing changes to the scope baseline is called:
- Validate Scope
- Control Scope (Correct answer)
- Define Scope
- Plan Scope Management
Correct answer: Control Scope
Control Scope is the process of monitoring scope status and managing changes to ensure the scope baseline is maintained.
Question 7: In agile projects, the product backlog most closely corresponds to which traditional PM artifact?
- Project charter
- Scope statement and requirements documentation (Correct answer)
- Risk register
- Stakeholder register
Correct answer: Scope statement and requirements documentation
The product backlog serves as the evolving list of features and requirements, functioning similarly to the scope statement and requirements documentation in predictive approaches.
A WBS dictionary primarily serves to: