Project Management Agile and Scrum Ceremonies 4 — Questions and Answers
Question 1: A Product Owner wants to cancel a Sprint. Under what condition does the Scrum Guide permit Sprint cancellation?
- When the team's velocity drops significantly
- When the Sprint Goal becomes obsolete (Correct answer)
- When more than half the Sprint Backlog is incomplete
- When a key developer leaves the team
Correct answer: When the Sprint Goal becomes obsolete
Only the Product Owner can cancel a Sprint, and only when the Sprint Goal becomes obsolete due to changed priorities, business conditions, or company direction.
Question 2: In SAFe (Scaled Agile Framework), what ceremony replaces the individual Sprint Review at the program level?
- Program Increment Planning
- System Demo (Correct answer)
- Inspect and Adapt Workshop
- Release Train Engineer sync
Correct answer: System Demo
The System Demo in SAFe is the program-level equivalent of the Sprint Review, where all Agile Release Train teams demonstrate integrated working software.
Question 3: What three questions traditionally structure the Daily Scrum?
- What did I plan, what did I do, why is there a gap?
- What did I do yesterday, what will I do today, are there any impediments? (Correct answer)
- What is my status, what is my priority, what help do I need?
- What is done, what is in progress, what is blocked?
Correct answer: What did I do yesterday, what will I do today, are there any impediments?
The traditional Daily Scrum uses three questions: what was accomplished yesterday, what will be done today, and what impediments exist — though the Scrum Guide now allows any structure that meets the goal.
Question 4: A Scrum Master observes that the team's Sprint Retrospectives produce action items that are never completed. What is the best response?
- Stop holding Retrospectives until team culture improves
- Add retrospective action items to the Sprint Backlog (Correct answer)
- Report the team to management
- Replace the retrospective with a written survey
Correct answer: Add retrospective action items to the Sprint Backlog
Adding retrospective improvement actions to the Sprint Backlog makes them visible, tracked, and prioritized alongside other work, increasing the chance of completion.
Question 5: Which Scrum event provides the opportunity for the Scrum Team to inspect the Definition of Done and improve it?
- Daily Scrum
- Sprint Review
- Sprint Planning
- Sprint Retrospective (Correct answer)
Correct answer: Sprint Retrospective
The Sprint Retrospective is where the team inspects their processes, tools, and quality standards — including reviewing and strengthening the Definition of Done.
Question 6: An Agile coach recommends 'timeboxing' all meetings. What is the primary benefit of timeboxing Scrum ceremonies?
- It ensures all agenda items are covered
- It creates urgency and prevents waste from open-ended discussions (Correct answer)
- It allows more meetings to be scheduled per day
- It replaces the need for a facilitator
Correct answer: It creates urgency and prevents waste from open-ended discussions
Timeboxing creates a sense of urgency that focuses discussion, prevents rambling conversations, and respects team members' time — a core Scrum discipline.
Question 7: During Sprint Planning, the Development Team determines they cannot complete all items the Product Owner wants. What should happen?
- The Product Owner overrides the team and adds the items anyway
- The team negotiates scope with the Product Owner to fit the Sprint capacity (Correct answer)
- The Scrum Master decides what gets included
- The Sprint is extended to accommodate all items
Correct answer: The team negotiates scope with the Product Owner to fit the Sprint capacity
The Development Team owns the commitment to the Sprint Backlog and negotiates scope with the Product Owner to ensure the Sprint Goal is achievable within capacity.