โ† All Project Management Flashcard Decks

Risk Response Planning Flashcards

7 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Risk Response Planning flashcards as text
  1. A project manager wants to reduce the probability of a supplier delay risk by adding a second approved supplier. This strategy is BEST described as:

    Answer: Mitigate

    Adding a second supplier reduces the probability of the delay risk occurring, which is the definition of mitigation.

  2. A risk has been identified that exceeds the project manager's authority level to address. The BEST response is to:

    Answer: Escalate the risk to the sponsor or senior management

    Escalation is the appropriate strategy when a risk falls outside the project's authority or scope to address.

  3. Which of the following BEST describes a contingency plan?

    Answer: A pre-planned response that activates when a defined trigger event happens

    A contingency plan is a pre-defined response activated when a specific trigger (risk event) occurs.

  4. The 'Exploit' strategy for opportunities aims to:

    Answer: Ensure the opportunity definitely occurs

    Exploiting an opportunity means taking actions to ensure the positive event definitely happens, maximizing its probability to 100%.

  5. A project manager updates the project documents and risk register after completing Plan Risk Responses. Which document captures agreed-upon response strategies and risk owners?

    Answer: Risk report

    The risk report (introduced in PMBOK 6) consolidates overall risk exposure and individual risk information including responses and ownership.

  6. A risk response that reduces the financial impact of a risk by negotiating a fixed-price contract with a vendor is BEST categorized as:

    Answer: Transfer

    A fixed-price contract shifts the financial risk of cost overruns to the vendor, making it a transfer strategy.

  7. After all planned responses are implemented, the remaining risk exposure is known as:

    Answer: Residual risk

    Residual risk is the remaining risk that persists after responses have been implemented and accepted by stakeholders.