Risk Management and Mitigation Flashcards

7 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Risk Management and Mitigation flashcards as text
  1. A project sponsor asks for a single number that summarizes the overall risk exposure of the project. Which technique BEST provides this?

    Answer: Expected Monetary Value (EMV) analysis

    EMV multiplies the probability of each risk by its monetary impact and sums them up to produce an overall risk exposure figure.

  2. Which of the following is an example of an 'opportunity' in the context of project risk management?

    Answer: A vendor delivering materials two weeks early, freeing up schedule buffer

    In risk management, opportunities are uncertain events with positive impacts on project objectives, such as early delivery that adds schedule float.

  3. What is the purpose of a 'risk register' in project management?

    Answer: To document identified risks, their characteristics, and planned responses

    The risk register is a central document that captures all identified risks, their probability, impact, owners, and planned response strategies.

  4. During Monte Carlo simulation for schedule risk analysis, what is the PRIMARY output?

    Answer: A probability distribution of possible project completion dates

    Monte Carlo simulation runs thousands of schedule scenarios to produce a probability distribution showing the likelihood of finishing by various dates.

  5. A project is facing a risk that the project team cannot control or mitigate. What is the MOST appropriate response strategy?

    Answer: Escalate

    Escalation is used when a risk is outside the project manager's authority or control and must be handled at a higher organizational level.

  6. Which document establishes the thresholds and processes for managing risk on a project?

    Answer: Risk management plan

    The risk management plan defines how risk management activities will be structured, including roles, methodologies, risk categories, and thresholds.

  7. A construction project is delayed because flooding damaged the site—an event that was identified but accepted. What is the PM's FIRST step now that the risk has occurred?

    Answer: Execute the planned contingency response

    When an accepted risk event occurs, the project manager should immediately execute the pre-planned contingency response to minimize impact.