Project Scope and WBS Flashcards

7 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Scope and WBS flashcards as text
  1. During scope planning, a project manager holds a structured meeting with key stakeholders to rapidly collect requirements. This technique is called:

    Answer: Facilitated workshop (JAD session)

    Facilitated workshops (such as JAD sessions) bring stakeholders together to quickly align on and document requirements.

  2. A project manager is creating the WBS and is unsure how far to decompose a deliverable. The best stopping point is when:

    Answer: The work can be realistically estimated, assigned, and managed

    Decomposition should stop when each component can be accurately estimated, clearly assigned, and effectively monitored.

  3. Which of the following scenarios best represents gold plating by a team member?

    Answer: Adding an unrequested animation to a software interface after the feature was approved

    Adding unrequested features, even well-intentioned ones, constitutes gold plating and violates scope discipline.

  4. The Plan Scope Management process produces which two key outputs?

    Answer: Scope management plan and requirements management plan

    Plan Scope Management produces the scope management plan (how scope will be defined and controlled) and the requirements management plan (how requirements will be tracked).

  5. A project manager notices that Validate Scope is repeatedly skipped during phase gate reviews. The most significant risk this creates is:

    Answer: Delivering a product that does not meet stakeholder expectations or acceptance criteria

    Skipping Validate Scope means deliverables are not formally accepted, increasing the risk of rework or rejection at project close.

  6. Which of the following best describes a constraint in a project scope statement?

    Answer: A limiting factor such as a fixed deadline or budget cap that affects scope decisions

    Constraints are restrictions like budget ceilings, regulatory requirements, or fixed dates that bound what is possible within the project scope.

  7. A change request is approved that significantly expands the project scope. What must the project manager update immediately?

    Answer: The scope baseline and all affected project management plan components

    An approved scope change requires updating the scope baseline (scope statement, WBS, WBS dictionary) and any related plan components such as schedule and cost baselines.