Project Scope and Quality Flashcards
6 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 Project Scope and Quality flashcards as text
A project manager is overseeing the development of a new software application. The development team has completed a module which they believe is ready for delivery. Which process should be performed NEXT to ensure the deliverable is correct and meets quality standards before presenting it to the client?
Answer: Control Quality
Control Quality is the process of monitoring and recording the results of executing quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. This internal process verifies the deliverable against the quality requirements and standards. It should be done before Validate Scope, which is the process of formalizing acceptance of the completed deliverables with the stakeholders.
Which of the following are all components of the scope baseline?
Answer: Project Scope Statement, WBS, and WBS Dictionary
The scope baseline is the approved version of the project scope. It is a component of the project management plan and consists of the approved project scope statement, the Work Breakdown Structure (WBS), and its associated WBS dictionary.
During a weekly status meeting for a construction project, a key stakeholder suggests adding an additional room to the building, which was not part of the original plan. This represents a potential change to the project's:
Answer: Scope
The project scope defines all the work required to complete the project deliverables. Adding a new room is a significant change to the features and work required, directly impacting the project scope. This situation is a classic example of potential scope creep.
The primary purpose of the Validate Scope process is to:
Answer: Obtain formal acceptance of the completed project deliverables from the stakeholders.
The Validate Scope process is primarily concerned with obtaining formal acceptance of the completed project deliverables from the project sponsor or customer. It is focused on the acceptance of the deliverables, whereas Control Quality is focused on the correctness of the deliverables.
A project team is in the Plan Quality Management process. Which of the following activities is the team MOST likely to be engaged in?
Answer: Identifying relevant quality standards and documenting how the project will demonstrate compliance.
Plan Quality Management is the process of identifying quality requirements and/or standards for the project and its deliverables and documenting how the project will demonstrate compliance with them. Using a Pareto diagram and peer reviews are part of Control Quality and Manage Quality, while formal acceptance is part of Validate Scope.
A Work Breakdown Structure (WBS) dictionary is created to support the WBS. What is the main purpose of the WBS dictionary?
Answer: To provide detailed information about the deliverables, activities, and scheduling of each WBS component.
The WBS dictionary provides detailed information for each component in the WBS, including a description of the work, responsible party, schedule milestones, required resources, and acceptance criteria. It complements the WBS, which only provides a hierarchical breakdown of the work.