โ† All Project Management Flashcard Decks

Project Cost Management Flashcards

7 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Cost Management flashcards as text
  1. A project's EAC using the formula EAC = AC + (BAC - EV) / CPI assumes:

    Answer: Future work will continue at the current CPI

    EAC = AC + (BAC - EV) / CPI assumes the current cost efficiency (CPI) will persist for all remaining work.

  2. What is the difference between contingency reserves and management reserves?

    Answer: Contingency reserves are for known unknowns; management reserves are for unknown unknowns

    Contingency reserves address identified risks (known unknowns), while management reserves cover unforeseen situations (unknown unknowns).

  3. Which document authorizes spending on a project and links the project to the organization's ongoing work?

    Answer: Project charter

    The project charter formally authorizes the project and gives the project manager authority to apply resources, including budget.

  4. Life cycle costing considers:

    Answer: Total cost of ownership including operation and maintenance

    Life cycle costing evaluates the total cost of ownership over the product's entire life, including acquisition, operations, and disposal.

  5. A project manager applies earned value analysis and finds Cost Variance (CV) = +$15,000. This means:

    Answer: The project is $15,000 under budget

    CV = EV - AC; a positive CV means earned value exceeds actual cost, so the project is under budget.

  6. Which output of the Control Costs process directly updates the cost baseline?

    Answer: Approved change requests

    Only formally approved change requests can authorize changes to the cost baseline through integrated change control.

  7. A project manager is presenting funding requirements to stakeholders. These are typically derived from which document?

    Answer: Cost baseline

    Funding requirements, including total and periodic funding needs, are derived from the cost baseline developed in the Determine Budget process.