Concept Flashcards

16 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 16 Concept flashcards as text
  1. A project manager has recently been given the project charter and preliminary project scope statement as well as been assigned to a new project. The project manager's initial task is to:

    Answer: Confirm that all the stakeholders have contributed to the scope.

    Upon receiving the project charter and preliminary scope, a project manager's initial critical task is to engage with stakeholders to ensure their requirements and expectations are fully understood and incorporated into the project scope. This proactive engagement helps prevent scope creep, ensures alignment, and builds a solid foundation for project success. Confirming stakeholder input on scope is foundational before proceeding with detailed planning.

  2. A group of connected projects that are coordinatedly handled and typically have a component of continuous activity is referred to as a:

    Answer: Program

    A program is defined as a group of related projects, subsidiary programs, and program activities managed in a coordinated way to obtain benefits not available from managing them individually. Programs often include an element of ongoing operational activity and are focused on achieving strategic objectives that span beyond a single project's scope.

  3. The formalization of approval and orderly completion of the project is a

    Answer: Closing

    The closing process group involves the formalization of approval and the orderly completion of the project or phase. This includes obtaining final sign-off, releasing resources, archiving project documents, and conducting lessons learned. It ensures that all work is completed, all contractual obligations are met, and the project is formally brought to an end.

  4. Which of the following general guidelines should you abide by when interacting with project stakeholders?

    Answer: Don’t assume, ask.

    Effective stakeholder engagement relies heavily on clear, open, and proactive communication. Project managers should never assume they understand stakeholders' needs, expectations, or concerns without direct verification. Actively asking questions, listening carefully, and seeking clarification ensures mutual understanding, builds trust, and prevents misinterpretations that could lead to project issues.

  5. A project manager is reevaluating the project to estimate project length in order to manage the timeline. She accomplishes this by examining the order of tasks with the least amount of scheduling latitude. What method is she employing?

    Answer: Critical path method

    The Critical Path Method (CPM) is a schedule network analysis technique used to determine the longest path of planned activities to the end of the project. Activities on this path have the 'least amount of scheduling latitude' (zero float), meaning any delay to them will directly delay the entire project. The project manager is using CPM to identify and manage these critical activities.

  6. The project charter has been signed by six people when you take over a project during the planning stage. Which of these issues needs your attention the most?

    Answer: Determining the reporting structure

    With multiple signatories on the project charter, there's a significant risk of conflicting directives and unclear lines of authority. The most immediate concern for a project manager is to clarify the reporting structure and identify a single, primary sponsor or decision-maker. This ensures clear direction, prevents confusion, and establishes accountability for project decisions.

  7. The project's ______ demand is noted to increase from the beginning to an intermediate stage of the project while it is being carried out.

    Answer: Resource

    During the execution phase of a project, the demand for resources (such as human resources, equipment, and materials) typically follows a bell-shaped curve. It starts low during initiation and planning, increases significantly as the main project work gets underway in the intermediate stages, and then tapers off towards the end as tasks are completed. This reflects the intensive activity during project delivery.

  8. Plan for configuration management is:

    Answer: The set of procedures developed to control changes.

    A configuration management plan defines the procedures for managing changes to the project's deliverables and documentation throughout its lifecycle. It establishes baselines, identifies how changes will be requested, evaluated, approved, tracked, and implemented. This ensures that the project's product and documentation remain consistent, controlled, and accurately reflect the current state.

  9. The job identified at the lowest level of the breakdown structure that involves time and cost estimation and management is known as the:

    Answer: Work Package

    A work package is the lowest level of the Work Breakdown Structure (WBS) and represents a manageable unit of work. It is the point at which work is scheduled, estimated for time and cost, monitored, and controlled. Work packages are assigned to specific teams or individuals, providing clear scope and accountability for completion.

  10. The project may experience ________ as it moves forward due to various external factors.

    Answer: Change

    Projects are inherently dynamic and operate within environments subject to various external influences. These external factors, such as market shifts, regulatory changes, or technological advancements, frequently necessitate adjustments to the project plan, scope, or schedule. Therefore, a project is highly likely to experience 'Change' as it progresses, requiring adaptability and a robust change management process.

  11. A project recently received the services of a project manager. The project's existence is acknowledged in a document known as:

    Answer: The project charter

    The project charter is a foundational document in project management that formally authorizes the existence of a project. It provides the project manager with the authority to apply organizational resources to project activities. This document is crucial as it officially acknowledges the project and outlines its purpose, objectives, and key stakeholders.

  12. The project's WBS represents:

    Answer: All the work must be completed for the project.

    The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the required deliverables. It defines all the work that must be completed for the project, organizing it into manageable sections. The WBS serves as a comprehensive, deliverable-oriented breakdown, ensuring no necessary work is overlooked.

  13. A normal _____ network must allow information, inquiries, comments, and views to circulate within the organization.

    Answer: Communication

    Effective communication is vital for any organization or project to function smoothly. A robust communication network facilitates the exchange of information, inquiries, comments, and views among team members and stakeholders. This continuous flow of information is essential for collaboration, decision-making, and ensuring everyone is aligned with project goals.

  14. The project manager should work with a _____ and do checks as often as feasible.

    Answer: System Administrator

    When the question implies working with systems and performing checks, the most appropriate professional is a System Administrator. This role is responsible for the upkeep, configuration, and reliable operation of computer systems, especially multi-user computers such as servers. Regular checks with a System Administrator ensure the technical infrastructure supporting the project runs efficiently and securely.

  15. Accepted change requests provide data for:

    Answer: Direct and Manage Project Work

    Accepted change requests are formal approvals to modify project baselines or components. These approved changes serve as direct inputs to the 'Direct and Manage Project Work' process, which is where the project manager and team perform the work defined in the project management plan. Implementing these changes ensures that the project's execution aligns with the latest approved requirements and scope.

  16. As an illustration of scope validation:

    Answer: Reviewing the performance of an installed software module.

    Scope validation is the process of formalizing acceptance of the completed project deliverables by the customer or sponsor. Reviewing the performance of an installed software module directly relates to verifying that the deliverable meets the specified requirements and is acceptable to the client. This step is crucial for gaining official sign-off and moving towards project closure.