← All Project Management Flashcard Decks

Earned Value Management (EVM) Flashcards

7 cards from real Project Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Earned Value Management (EVM) flashcards as text
  1. A project has BAC = $500,000, CPI = 0.90, and is 60% complete by EV. A new EAC is needed assuming past performance continues. What is the EAC?

    Answer: $555,556

    EAC = BAC / CPI = $500,000 / 0.90 ≈ $555,556, reflecting that inefficiency will persist through project completion.

  2. Which of the following best describes the Variance at Completion (VAC)?

    Answer: The projected difference between BAC and EAC

    VAC = BAC - EAC; it predicts whether the project will be over or under budget at the end.

  3. A project manager observes CPI = 0.75 and SPI = 0.85. What is the most accurate conclusion?

    Answer: The project is both over budget and behind schedule

    CPI < 1 means over budget and SPI < 1 means behind schedule, so both performance dimensions are unfavorable.

  4. What is the primary purpose of the Performance Measurement Baseline (PMB) in EVM?

    Answer: To provide the integrated scope, schedule, and cost baseline against which project performance is measured

    The PMB integrates scope, schedule, and cost and serves as the reference point for measuring project performance variances.

  5. A work package has a BAC of $10,000, is 50% complete by EV, and has spent $6,000. What is the Cost Variance (CV)?

    Answer: -$1,000

    EV = 50% × $10,000 = $5,000; CV = EV - AC = $5,000 - $6,000 = -$1,000, indicating a cost overrun.

  6. Which EVM technique assigns 100% credit only when the work package is fully completed?

    Answer: 0/100 method

    The 0/100 method assigns no earned value until the work is complete, then grants 100% — ideal for short-duration tasks.

  7. During a project review, the EAC is recalculated using EAC = AC + (BAC - EV). When is this formula most appropriate?

    Answer: When the remaining work will be performed at the original budgeted rate despite past overruns

    This formula assumes the cost overrun to date was a one-time event and future work will proceed as originally planned.