Program Management Professional Practice Test
Program Management Professional Program Financial Management 3
What does a Schedule Performance Index (SPI) greater than 1.0 indicate?
Select your answer
A
The program is over budget
B
The program is ahead of schedule β more work has been accomplished than planned
C
The program is behind schedule
D
The program has exceeded its scope
Hint