Question 1: What is the MOST important outcome of a Sprint Review in the context of managing products with agility?
- Formal sign-off on completed features by all stakeholders
- Updated velocity metrics for future Sprint planning
- Shared understanding of progress and an updated Product Backlog reflecting new insights (Correct answer)
- A written report of all bugs found during the Sprint
Correct answer: Shared understanding of progress and an updated Product Backlog reflecting new insights
The Sprint Review's key output is an adapted Product Backlog that incorporates stakeholder feedback and new information, enabling smarter decisions in the next Sprint.
Question 2: A Product Owner is working on a new product with high market uncertainty. Which approach BEST manages this risk?
- Spend six months on market research before committing to a Product Goal
- Build the full product as planned to minimize changes during development
- Use short Sprints to release small Increments quickly and validate assumptions with real users (Correct answer)
- Hire a market research firm to predict the right features before development begins
Correct answer: Use short Sprints to release small Increments quickly and validate assumptions with real users
Short feedback loops through frequent Increments allow the team to validate assumptions early and cheaply, reducing the risk of building the wrong product.
Question 3: Which statement about the Product Owner's authority over the Product Backlog is CORRECT?
- The Product Owner must get consensus from all stakeholders before ordering the backlog
- The Product Owner has sole authority to order the Product Backlog and may consider stakeholder input (Correct answer)
- The Development Team has final say on backlog ordering because they do the work
- The Scrum Master must approve all backlog changes before Sprint Planning
Correct answer: The Product Owner has sole authority to order the Product Backlog and may consider stakeholder input
The Product Owner is solely accountable for Product Backlog management, including ordering; they gather stakeholder input but make the final call.
Question 4: What is the BEST way for a Product Owner to communicate the product vision to a newly formed Scrum Team?
- Distribute a written specification document covering all planned features
- Share the Product Goal and product vision through collaborative conversations, ensuring the team understands the 'why' behind the work (Correct answer)
- Present a detailed Gantt chart showing all delivery milestones
- Assign the vision document to the Scrum Master to relay to the team
Correct answer: Share the Product Goal and product vision through collaborative conversations, ensuring the team understands the 'why' behind the work
Shared understanding of vision is built through dialogue and collaboration, ensuring every team member can make decisions aligned with the product's purpose.
Question 5: A Product Owner notices that the Development Team consistently delivers fewer items than forecasted each Sprint. What should the Product Owner investigate FIRST?
- Whether the team is working enough hours each day
- Whether backlog items are well-refined and the Definition of Done is clear and achievable (Correct answer)
- Whether story point estimates need to be reduced
- Whether the Sprint length should be shortened to one week
Correct answer: Whether backlog items are well-refined and the Definition of Done is clear and achievable
Consistently missing forecasts often signals that items entering Sprint Planning are unclear, too large, or that the Definition of Done creates unexpected rework.
Question 6: How does a Product Owner balance short-term stakeholder requests with the long-term Product Goal?
- Always prioritize long-term goals and reject all short-term requests
- Always satisfy immediate stakeholder requests to maintain relationships
- Evaluate short-term requests against the Product Goal and order them relative to long-term value (Correct answer)
- Let the Scrum Master decide which requests align with the Product Goal
Correct answer: Evaluate short-term requests against the Product Goal and order them relative to long-term value
The Product Owner uses the Product Goal as the lens to evaluate all requests, ordering short-term items where they deliver value without derailing long-term direction.
Question 7: When multiple Scrum Teams work on the same product, who is responsible for the Product Backlog?
- Each Scrum Team maintains its own separate Product Backlog
- One Product Owner is responsible for a single Product Backlog shared across all teams (Correct answer)
- The Scrum Masters coordinate backlog ownership across the teams
- Management assigns backlog sections to each team independently
Correct answer: One Product Owner is responsible for a single Product Backlog shared across all teams
One product has one Product Backlog and one Product Owner, regardless of how many Scrum Teams contribute to its development.