PRINCE2 Foundation Practice Test
PRINCE2 Managing a Stage Boundary 3
What is the key difference between a Stage Plan and an Exception Plan in PRINCE2?
Select your answer
A
A Stage Plan covers one management stage; an Exception Plan replaces a Stage Plan when tolerances are forecast to be exceeded
B
A Stage Plan is produced by the Project Board; an Exception Plan is produced by the Project Manager
C
A Stage Plan includes financial information; an Exception Plan focuses only on schedule recovery
D
A Stage Plan covers the whole project; an Exception Plan covers only a single work package
Hint