A project's Schedule Variance (SV) is โ$20,000 and Cost Variance (CV) is +$15,000. Which statement BEST describes the project status?
-
A
Behind schedule and over budget
-
B
Behind schedule but under budget
-
C
Ahead of schedule and under budget
-
D
Ahead of schedule but over budget