A project manager is evaluating contract types for a research project with highly uncertain scope. Which contract type best protects the buyer from bearing all risk?
-
A
Cost Plus Fixed Fee (CPFF)
-
B
Firm Fixed Price (FFP)
-
C
Time and Material (T&M)
-
D
Fixed Price with Economic Price Adjustment (FP-EPA)