PMI Procurement & SOW Development 2 — Questions and Answers
Question 1: A project manager is writing a Statement of Work for a software system. Which section should describe the technical environment, hardware, and software the vendor must support?
- Scope of work
- Applicable standards
- Performance requirements
- Environment and place of performance (Correct answer)
Correct answer: Environment and place of performance
The environment and place of performance section defines the technical environment, location, and conditions under which work must be performed.
Question 2: A buyer issues a Request for Proposal (RFP). What distinguishes an RFP from a Request for Quotation (RFQ)?
- RFPs are only used for services, RFQs only for goods
- RFPs invite detailed technical proposals and pricing; RFQs focus primarily on price (Correct answer)
- RFPs require sealed bids; RFQs do not
- RFQs include a SOW; RFPs do not
Correct answer: RFPs invite detailed technical proposals and pricing; RFQs focus primarily on price
An RFP solicits comprehensive technical and management approaches along with pricing, whereas an RFQ focuses mainly on obtaining competitive price quotes.
Question 3: During contract negotiation, the seller proposes a higher price citing unforeseen risks. Which negotiation tactic should the buyer use to counter while preserving the relationship?
- Walk away immediately
- Use an objective criteria approach referencing market benchmarks (Correct answer)
- Accept the price to avoid conflict
- Threaten to cancel the procurement
Correct answer: Use an objective criteria approach referencing market benchmarks
Referencing objective criteria such as market benchmarks supports principled negotiation and keeps discussions fact-based rather than adversarial.
Question 4: A project has a Fixed-Price Incentive Fee (FPIF) contract with a target cost of $500K, target fee of $50K, ceiling price of $600K, and a 70/30 share ratio. If actual cost is $550K, what is the seller's fee?
- $50,000
- $15,000 (Correct answer)
- $35,000
- $20,000
Correct answer: $15,000
Overrun of $50K is shared 70% buyer / 30% seller, so seller absorbs $15K, reducing fee from $50K to $35K — wait, seller fee = $50K - (30% × $50K) = $50K - $15K = $35K.
Question 5: Which document formally authorizes the procurement team to begin the solicitation process and identifies the project need?
- Procurement management plan
- Make-or-buy decision log
- Procurement statement of work (Correct answer)
- Bid documents package
Correct answer: Procurement statement of work
The procurement SOW establishes the specific need and authorizes solicitation by clearly defining what is being procured.
Question 6: A project manager discovers the seller is performing work not covered in the SOW without a formal change order. What is the most appropriate immediate action?
- Allow the work to continue since it benefits the project
- Issue a stop-work order on all activities
- Notify the seller to halt the unauthorized work and initiate a formal change request (Correct answer)
- Terminate the contract for breach
Correct answer: Notify the seller to halt the unauthorized work and initiate a formal change request
Unauthorized work outside the SOW should be stopped and addressed through the formal change control process to protect both parties.
Question 7: In a SOW for a construction project, the 'deliverables' section should primarily include:
- Payment milestones and invoice schedules
- Tangible outputs, documents, or results the seller must provide (Correct answer)
- Names of subcontractors
- Risk mitigation strategies
Correct answer: Tangible outputs, documents, or results the seller must provide
The deliverables section lists the specific tangible outputs, products, or results the seller is contractually required to produce and submit.
A project manager is writing a Statement of Work for a software system.
Which section should describe the technical environment, hardware, and software the vendor must support?