A project manager is using a cumulative CPI of 0.75 and the project has $400,000 remaining in BAC. Which EAC formula is most appropriate when assuming current inefficiencies will continue?
-
A
EAC = AC + (BAC - EV)
-
B
EAC = BAC / CPI
-
C
EAC = AC + ETC (new estimate)
-
D
EAC = AC + (BAC - EV) / (CPI × SPI)