PMI-SP Time Estimating & Resource Allocation 5 — Questions and Answers
Question 1: Which estimating technique is MOST appropriate early in a project when detailed scope information is not yet available?
- Bottom-up estimating
- Parametric estimating
- Analogous estimating (Correct answer)
- Three-point estimating
Correct answer: Analogous estimating
Analogous estimating uses expert judgment and historical data from similar projects, making it suitable when detailed information is limited in early phases.
Question 2: A project scheduler needs to assess schedule risk across multiple paths. Which technique uses duration probability distributions to simulate thousands of possible outcomes?
- Critical path method (CPM)
- Program evaluation and review technique (PERT)
- Monte Carlo simulation (Correct answer)
- Resource leveling
Correct answer: Monte Carlo simulation
Monte Carlo simulation runs thousands of iterations using statistical distributions of activity durations to produce a probability distribution of project completion dates.
Question 3: An activity requiring 160 hours of effort is assigned to two resources working in parallel at 100% capacity each. If each resource works 8 hours per day, what is the activity duration?
- 20 days
- 10 days (Correct answer)
- 16 days
- 40 days
Correct answer: 10 days
Two resources working in parallel provide 16 hours per day combined, so 160 hours / 16 hours per day = 10 days duration.
Question 4: What is the key difference between effort and duration in activity estimating?
- Effort is measured in cost; duration is measured in time
- Effort is the total work hours required; duration is the elapsed calendar time (Correct answer)
- Effort applies to resources; duration applies to materials
- Effort is always greater than or equal to duration
Correct answer: Effort is the total work hours required; duration is the elapsed calendar time
Effort measures the total amount of work (person-hours) needed, while duration measures the calendar time from start to finish including non-working time.
Question 5: When applying the critical chain method, buffers are placed at the end of the project to protect which schedule element?
- Individual activity float
- The project completion date (Correct answer)
- Resource availability windows
- Milestone dates for all phases
Correct answer: The project completion date
Critical chain adds a project buffer at the end of the critical chain to protect the project's final completion date from uncertainty in individual activities.
Question 6: A resource is assigned to five projects simultaneously. Which tool would BEST help the project scheduler identify the impact on a specific project's schedule?
- WBS dictionary
- Resource breakdown structure
- Multi-project resource histogram (Correct answer)
- Risk register
Correct answer: Multi-project resource histogram
A multi-project resource histogram shows resource demand across all projects over time, making it easy to spot over-allocations affecting any single project.
Question 7: Which statement BEST describes the relationship between activity sequencing and resource allocation in schedule development?
- Resource allocation must be completed before activity sequencing begins
- Activity sequencing defines dependencies; resource allocation may further constrain the sequence (Correct answer)
- Resource allocation replaces the need for dependency analysis
- Activity sequencing and resource allocation are performed in completely separate phases with no interaction
Correct answer: Activity sequencing defines dependencies; resource allocation may further constrain the sequence
Activity sequencing establishes logical dependencies, but resource constraints can impose additional limitations that alter when activities can actually be performed.
Which estimating technique is MOST appropriate early in a project when detailed scope information is not yet available?