PMI-SP Schedule Tools 3 — Questions and Answers
Question 1: Which scheduling tool output best supports stakeholder communications by showing only key deliverables and their planned completion dates?
- Resource histogram
- Milestone schedule (Correct answer)
- Network diagram
- S-curve report
Correct answer: Milestone schedule
Milestone schedules highlight key deliverables and dates, providing an executive-level view without task-level detail.
Question 2: A scheduler sets a 'Must Finish On' constraint in scheduling software. How does this differ from a 'Finish No Later Than' constraint?
- 'Must Finish On' is flexible; 'Finish No Later Than' is rigid
- 'Must Finish On' locks the finish date exactly; 'Finish No Later Than' allows early finish (Correct answer)
- 'Must Finish On' applies only to milestones; the other applies to tasks
- Both constraints behave identically in the scheduling engine
Correct answer: 'Must Finish On' locks the finish date exactly; 'Finish No Later Than' allows early finish
'Must Finish On' pins the finish to a specific date regardless of float, while 'Finish No Later Than' allows the task to finish earlier if logic permits.
Question 3: When importing a schedule from another tool using XML format (e.g., Microsoft Project XML), the project manager should first verify:
- That all resources are color-coded correctly
- That dependencies, constraints, and calendars transferred accurately (Correct answer)
- That the Gantt chart bar styles match
- That baselines are automatically recalculated
Correct answer: That dependencies, constraints, and calendars transferred accurately
Import validation must confirm that logical relationships, date constraints, and calendar assignments survived the format conversion without data loss.
Question 4: In scheduling software, 'early start' (ES) and 'late start' (LS) dates are computed during which two passes of the scheduling algorithm?
- Resource leveling pass and optimization pass
- Forward pass and backward pass (Correct answer)
- Baseline pass and current pass
- Critical path pass and float pass
Correct answer: Forward pass and backward pass
The forward pass calculates ES and early finish, while the backward pass calculates LS and late finish, together determining float.
Question 5: A scheduling tool's baseline is best described as:
- The most recent status update to the schedule
- A snapshot of the approved plan against which actual performance is measured (Correct answer)
- A list of all project milestones agreed upon by stakeholders
- The resource-leveled version of the original schedule
Correct answer: A snapshot of the approved plan against which actual performance is measured
The baseline is a frozen copy of the approved schedule used as a reference for variance analysis throughout the project.
Question 6: Which scheduling tool feature automatically adjusts all successor task dates when a predecessor's duration changes?
- Auto-scheduling mode (Correct answer)
- Manual scheduling mode
- Constraint lock
- Resource pool synchronization
Correct answer: Auto-scheduling mode
Auto-scheduling mode calculates dates based on network logic, so changes to one task propagate through all successors automatically.
Question 7: A project manager needs to display actual progress against the baseline on a Gantt chart. Which visualization technique is typically used in scheduling tools?
- Earned value S-curve overlay
- Progress bar inside the baseline bar (Correct answer)
- Variance column in the task table
- Histogram showing planned vs. actual
Correct answer: Progress bar inside the baseline bar
Most scheduling tools render a progress bar (often shaded differently) inside or beside the baseline bar on the Gantt chart to show completion percentage vs. plan.
Which scheduling tool output best supports stakeholder communications by showing only key deliverables and their planned completion dates?