Which estimating technique is MOST appropriate early in a project when detailed scope information is not yet available?
Answer: Analogous estimating
Analogous estimating uses expert judgment and historical data from similar projects, making it suitable when detailed information is limited in early phases.
A project scheduler needs to assess schedule risk across multiple paths. Which technique uses duration probability distributions to simulate thousands of possible outcomes?
Answer: Monte Carlo simulation
Monte Carlo simulation runs thousands of iterations using statistical distributions of activity durations to produce a probability distribution of project completion dates.
An activity requiring 160 hours of effort is assigned to two resources working in parallel at 100% capacity each. If each resource works 8 hours per day, what is the activity duration?
Answer: 10 days
Two resources working in parallel provide 16 hours per day combined, so 160 hours / 16 hours per day = 10 days duration.
What is the key difference between effort and duration in activity estimating?
Answer: Effort is the total work hours required; duration is the elapsed calendar time
Effort measures the total amount of work (person-hours) needed, while duration measures the calendar time from start to finish including non-working time.
When applying the critical chain method, buffers are placed at the end of the project to protect which schedule element?
Answer: The project completion date
Critical chain adds a project buffer at the end of the critical chain to protect the project's final completion date from uncertainty in individual activities.
A resource is assigned to five projects simultaneously. Which tool would BEST help the project scheduler identify the impact on a specific project's schedule?
Answer: Multi-project resource histogram
A multi-project resource histogram shows resource demand across all projects over time, making it easy to spot over-allocations affecting any single project.
Which statement BEST describes the relationship between activity sequencing and resource allocation in schedule development?
Answer: Activity sequencing defines dependencies; resource allocation may further constrain the sequence
Activity sequencing establishes logical dependencies, but resource constraints can impose additional limitations that alter when activities can actually be performed.