Time Estimating & Resource Allocation Flashcards

7 cards from real PMI-SP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Time Estimating & Resource Allocation flashcards as text
  1. An activity has an optimistic estimate of 3 days, a pessimistic estimate of 15 days, and a most likely estimate of 6 days. What is the PERT expected duration?

    Answer: 7 days

    PERT = (3 + 4×6 + 15) / 6 = (3 + 24 + 15) / 6 = 42 / 6 = 7 days.

  2. What does a resource histogram primarily display?

    Answer: The amount of work planned for a resource over time

    A resource histogram is a bar chart showing the quantity of resource usage over the project timeline, making over-allocations visually apparent.

  3. Which technique reassigns non-critical tasks to off-peak periods to smooth resource demand without changing the project end date?

    Answer: Resource smoothing

    Resource smoothing adjusts activities within their available float to reduce peak resource demand while keeping the project finish date unchanged.

  4. A PMI-SP candidate needs to estimate effort for writing 50 test cases. Historical data shows a senior tester writes 5 test cases per day. What estimating technique uses this productivity rate?

    Answer: Parametric estimating

    Parametric estimating multiplies a unit productivity rate (5 test cases/day) by the quantity (50 test cases) to derive the effort estimate.

  5. When a project has a fixed end date and insufficient resources, which strategy is MOST appropriate?

    Answer: Add resources to critical path activities

    Adding resources to critical path activities (crashing) can compress the schedule to meet a fixed end date when resources are the constraint.

  6. The standard deviation of a PERT activity estimate is calculated as:

    Answer: (P - O) / 6

    The standard deviation for a PERT estimate is (Pessimistic - Optimistic) / 6, representing the uncertainty spread of the estimate.

  7. What term describes the maximum amount of time an activity can be delayed from its early start without delaying any successor activity?

    Answer: Free float

    Free float is the amount of time an activity can be delayed without affecting the early start of any immediately following activity.