Schedule Tools Flashcards

7 cards from real PMI-SP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Schedule Tools flashcards as text
  1. Which scheduling tool output best supports stakeholder communications by showing only key deliverables and their planned completion dates?

    Answer: Milestone schedule

    Milestone schedules highlight key deliverables and dates, providing an executive-level view without task-level detail.

  2. A scheduler sets a 'Must Finish On' constraint in scheduling software. How does this differ from a 'Finish No Later Than' constraint?

    Answer: 'Must Finish On' locks the finish date exactly; 'Finish No Later Than' allows early finish

    'Must Finish On' pins the finish to a specific date regardless of float, while 'Finish No Later Than' allows the task to finish earlier if logic permits.

  3. When importing a schedule from another tool using XML format (e.g., Microsoft Project XML), the project manager should first verify:

    Answer: That dependencies, constraints, and calendars transferred accurately

    Import validation must confirm that logical relationships, date constraints, and calendar assignments survived the format conversion without data loss.

  4. In scheduling software, 'early start' (ES) and 'late start' (LS) dates are computed during which two passes of the scheduling algorithm?

    Answer: Forward pass and backward pass

    The forward pass calculates ES and early finish, while the backward pass calculates LS and late finish, together determining float.

  5. A scheduling tool's baseline is best described as:

    Answer: A snapshot of the approved plan against which actual performance is measured

    The baseline is a frozen copy of the approved schedule used as a reference for variance analysis throughout the project.

  6. Which scheduling tool feature automatically adjusts all successor task dates when a predecessor's duration changes?

    Answer: Auto-scheduling mode

    Auto-scheduling mode calculates dates based on network logic, so changes to one task propagate through all successors automatically.

  7. A project manager needs to display actual progress against the baseline on a Gantt chart. Which visualization technique is typically used in scheduling tools?

    Answer: Progress bar inside the baseline bar

    Most scheduling tools render a progress bar (often shaded differently) inside or beside the baseline bar on the Gantt chart to show completion percentage vs. plan.