← All PMI-SP Flashcard Decks

Risk Analysis & Contingency Planning Flashcards

7 cards from real PMI-SP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Risk Analysis & Contingency Planning flashcards as text
  1. A project scheduler is using Monte Carlo simulation on a construction project. After 10,000 iterations, the P80 completion date is 3 weeks later than the deterministic schedule. What does this indicate?

    Answer: There is an 80% probability the project finishes on or before that date

    The P80 value in Monte Carlo simulation means there is an 80% probability the project will be completed on or before that date.

  2. Which of the following best describes the purpose of a risk register in schedule risk management?

    Answer: To record identified risks, their analysis results, and planned responses

    The risk register is the primary document for recording identified risks along with their probability, impact assessments, and planned response strategies.

  3. A PMI-SP practitioner identifies that a key vendor consistently delivers materials two weeks late. This is BEST categorized as:

    Answer: A known-unknown risk that can be planned for in the schedule

    A recurring vendor delay pattern is a known-unknown risk—identified and understood well enough to incorporate contingency or response plans into the schedule.

  4. When developing schedule contingency reserves, a project manager uses the expected monetary value (EMV) approach. A risk has a 30% probability of occurring and would cause a 10-day delay. What is the EMV of this schedule risk?

    Answer: 3 days

    EMV is calculated by multiplying probability (0.30) by impact (10 days), resulting in 3 days of schedule contingency contribution.

  5. A risk response strategy where the project team shifts the negative impact of a schedule risk to a third party is called:

    Answer: Transfer

    Transfer involves shifting the risk responsibility to a third party, such as through contracts, insurance, or performance bonds.

  6. During qualitative risk analysis, a scheduler discovers a risk with high probability but very low schedule impact. This risk should MOST likely be:

    Answer: Placed on the watchlist for periodic monitoring

    Risks with high probability but low impact are typically placed on a watchlist and monitored rather than warranting immediate active response.

  7. A project schedule shows a critical path with zero float. When a risk event occurs that adds 5 days to a critical path activity, what is the direct effect on the project?

    Answer: The project finish date moves out by 5 days unless contingency reserves are used

    Critical path activities have zero float, so any delay directly extends the project completion date unless schedule reserves are applied.