  1. A scheduler is asked to forecast the project's completion date using the current SPI. Which formula applies?

    Answer: Forecast Duration = Planned Duration / SPI

    Dividing planned duration by current SPI extrapolates the expected total duration based on the current schedule efficiency rate.

  2. A project manager wants to determine whether recently observed schedule variances are systematic or random. Which statistical technique is MOST useful?

    Answer: Control Charts

    Control charts plot performance data over time and use control limits to distinguish systematic (assignable) variation from random (common cause) variation.

  3. During a schedule review, a stakeholder insists that a variance of +2 days on a non-critical activity with 15 days of total float requires immediate escalation. How should the PMI-SP respond?

    Answer: Explain that the activity still has 13 days of remaining float and does not yet threaten the critical path

    With 13 days of remaining float, the activity has adequate buffer and escalation is premature; the PMI-SP should educate the stakeholder on float.

  4. Which component of the Project Management Information System (PMIS) is MOST critical for real-time schedule monitoring?

    Answer: Scheduling software with live progress update capabilities

    Scheduling software (e.g., Primavera, MS Project) with real-time update features allows the team to immediately see the impact of progress updates on the schedule.

  5. A schedule report shows that 80% of activities on the critical path have SPI < 0.85. What type of corrective action warrants consideration FIRST?

    Answer: Fast-tracking or crashing critical path activities to recover lost time

    When critical path performance is significantly below plan, schedule compression techniques like fast-tracking or crashing are the primary recovery levers.

  6. A project sponsor requires a 'stoplight' schedule report each Friday. Green, yellow, and red indicators are tied to SPI thresholds. What is the PRIMARY benefit of this approach?

    Answer: It provides at-a-glance exception-based reporting that focuses attention on problem areas

    Stoplight/RAG reporting uses color thresholds to surface exceptions quickly, enabling busy stakeholders to focus on areas needing attention.

  7. When schedule control reveals that a vendor delivery date will slip by 3 weeks, which document should the PMI-SP update FIRST to reflect this new risk to the schedule?

    Answer: Risk Register

    The Risk Register should be updated to log the schedule risk from the vendor slip, triggering risk response planning if thresholds are exceeded.