  1. What is a 'baseline at completion' (BAC) in the context of schedule performance?

    Answer: The total budgeted cost for all work in the approved baseline

    Budget at Completion (BAC) represents the total authorized budget for all work scope as defined in the approved baseline.

  2. A project has multiple approved baselines over its life due to significant scope changes. Which version should be used for current performance reporting?

    Answer: The most recently approved baseline

    Performance should always be measured against the most recently approved baseline, which reflects the currently authorized scope, schedule, and budget.

  3. A schedule baseline shows a planned finish of Q4. A risk event occurs and adds 8 weeks. The risk was included in the risk register with a contingency reserve. What is the correct baseline action?

    Answer: Use the contingency reserve; update only the working schedule until the CCB approves a baseline change if needed

    Contingency reserve is meant to handle identified risks; the project manager uses the reserve and only seeks a baseline change if the impact exceeds the reserve.

  4. Which PMI-SP competency area is most directly responsible for maintaining baseline integrity throughout the project lifecycle?

    Answer: Schedule control and change management

    Schedule control and change management ensure that the baseline is protected from unauthorized changes and updated properly when changes are approved.

  5. A project manager wants to establish a baseline but the WBS is only 60% complete. What is the recommended approach?

    Answer: Use rolling wave planning to baseline known near-term work and plan far-term work in detail as it approaches

    Rolling wave planning allows a baseline to be set on near-term detailed work while far-term work is elaborated progressively, a recognized PMI best practice.

  6. During project closeout, the scheduler is asked to conduct a baseline variance analysis. What is the primary purpose of this analysis?

    Answer: To capture lessons learned about estimating and planning accuracy for future projects

    Post-project baseline variance analysis identifies estimation and planning gaps to improve accuracy on future projects, forming a key lessons-learned artifact.

  7. Which of the following is NOT a valid reason to formally re-baseline a project schedule?

    Answer: The project team wants to avoid showing a large schedule variance

    Re-baselining solely to erase unfavorable variances is unethical and not a valid reason; baselines must reflect authorized changes, not performance problems.