Activity Sequencing Flashcards
7 cards from real PMI-SP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Activity Sequencing flashcards as text
A project scheduler is modeling a situation where Activity B cannot start until 5 days after Activity A starts. Which type of dependency relationship best represents this?
Answer: Start-to-Start with 5-day lag
A Start-to-Start (SS) relationship with a 5-day lag means B cannot start until 5 days after A starts.
Which sequencing method uses arrow diagrams where arrows represent activities and nodes represent events?
Answer: Arrow Diagramming Method (ADM)
The Arrow Diagramming Method (ADM) uses arrows for activities and nodes for events, unlike PDM which uses nodes for activities.
A scheduler discovers that two activities were linked with a mandatory dependency due to a contractual requirement, not a physical one. How should this be classified?
Answer: Mandatory external dependency
A contractual requirement imposed by an external party creates a mandatory external dependency.
In a network diagram, Activity X has three predecessors: A (FS), B (FS+3 days lag), and C (FS-2 days lead). If A finishes on Day 10, B finishes on Day 8, and C finishes on Day 12, when is the earliest X can start?
Answer: Day 11
X's early start = max(10+0, 8+3, 12-2) = max(10, 11, 10) = Day 11.
Which term describes a dependency that originates within the performing organization's own control or project scope?
Answer: Internal dependency
Internal dependencies are relationships between project activities that are within the control of the project team.
A project manager wants to use fast tracking to compress the schedule. Which sequencing technique supports this approach?
Answer: Replacing FS relationships with SS or FF relationships with leads
Fast tracking overlaps activities by replacing FS links with SS/FF relationships or applying leads, allowing parallel work.
In the Precedence Diagramming Method, which relationship type is LEAST commonly used in practice?
Answer: Start-to-Finish (SF)
Start-to-Finish (SF) is rarely used in practice; it means the successor cannot finish until the predecessor starts.