What is the primary purpose of identifying stakeholders during the risk management planning process?
-
A
To assign risk owners to all identified risks
-
B
To understand their risk appetite, tolerance, and influence on risk management decisions
-
C
To create a communication plan for project status updates
-
D
To establish the risk management budget