PMI-RMP Certification Stakeholder Engagement in Risk Management 3
Which element of the stakeholder register is most directly relevant to risk management planning?
Select your answer
A
Stakeholder contact information and preferred communication channels
B
Stakeholder risk appetite, influence level, and desired degree of risk engagement
C
Stakeholder performance ratings from previous projects
D
Stakeholder position on the organizational chart