Project Budgeting & Financial Control Flashcards
7 cards from real PMI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Budgeting & Financial Control flashcards as text
A project manager calculates the Estimate at Completion (EAC) assuming future work will be performed at the budgeted rate. Which formula applies?
Answer: EAC = AC + (BAC − EV)
When future work is assumed to proceed at the planned rate, EAC = AC + (BAC − EV), using remaining budget as the ETC.
Which cost management output establishes how cost variances will be managed and what thresholds trigger corrective action?
Answer: Cost management plan
The cost management plan defines variance thresholds, reporting formats, and procedures for managing cost deviations.
A project has BAC = $800,000, PV = $400,000, EV = $360,000, and AC = $420,000. What is the Schedule Performance Index (SPI)?
Answer: 0.900
SPI = EV / PV = $360,000 / $400,000 = 0.90, indicating the project is progressing at 90% of the planned rate.
When should a project manager create a new EAC rather than using a formula-based forecast?
Answer: When the original estimate is fundamentally flawed and actual costs are known
A ground-up EAC is appropriate when the original estimate is no longer valid and actual performance data enables a more reliable re-estimate.
Which of the following BEST describes 'sunk costs' in project financial management?
Answer: Costs already incurred that should not influence future decisions
Sunk costs are past expenditures that cannot be recovered and should not factor into forward-looking project decisions.
A project manager is asked to use life-cycle costing. What does this approach consider?
Answer: All costs from project initiation through product retirement
Life-cycle costing evaluates total cost of ownership including acquisition, operations, maintenance, and disposal costs.
Which tool helps a project manager identify the statistical probability of completing a project within a given cost range?
Answer: Monte Carlo simulation
Monte Carlo simulation runs thousands of cost scenarios using probability distributions to produce a confidence-level cost range.