A project is 50% complete. The Budget at Completion (BAC) is $200,000, and the Actual Cost (AC) is $110,000. What is the Estimate at Completion (EAC) assuming the current CPI will continue?
Answer: $220,000
EV = 50% × $200,000 = $100,000; CPI = $100,000 / $110,000 = 0.909; EAC = BAC / CPI = $200,000 / 0.909 ≈ $220,000.
Which Integration Management process involves gathering and distributing performance information, including status reports, progress measurements, and forecasts?
Answer: Monitor and Control Project Work
Monitor and Control Project Work tracks, reviews, and reports overall project progress to meet the performance objectives defined in the project management plan.
A project manager discovers that the team is consistently gold-plating deliverables by adding unauthorized features. Which process should be strengthened?
Answer: Control Scope
Control Scope monitors scope changes and prevents unauthorized scope additions including gold-plating by enforcing the scope baseline.
A finish-to-start dependency with a lag of 5 days means:
Answer: Activity B cannot start until 5 days after Activity A finishes
A finish-to-start relationship with a 5-day lag means the successor activity (B) cannot begin until 5 days after the predecessor activity (A) has finished.
Which resource management tool shows the amount of work required by a resource over time and helps identify over-allocation?
Answer: Resource histogram
A resource histogram is a bar chart that shows the amount of work assigned to a resource over time, making over-allocation visually apparent.
In Risk Management, the risk response strategy of transferring a risk is BEST illustrated by which example?
Answer: Purchasing insurance or using a fixed-price contract
Risk transfer shifts the impact of a risk to a third party, such as purchasing insurance or using fixed-price contracts that place financial risk on the vendor.
Which closing activity ensures project records are archived, final payments are made, and team members are released in an organized manner?
Answer: Close Project or Phase
Close Project or Phase finalizes all activities, archives records, obtains acceptance, releases resources, and closes out contracts and procurements.