PMBOK Risk Management Processes 4 — Questions and Answers
Question 1: What is the Expected Monetary Value (EMV) of a risk with a 30% probability and a $50,000 negative impact?
- -$15,000 (Correct answer)
- -$35,000
- $15,000
- -$150,000
Correct answer: -$15,000
EMV = Probability × Impact = 0.30 × (-$50,000) = -$15,000, representing the weighted average outcome.
Question 2: Which risk process uses the probability and impact matrix as a key tool?
- Plan Risk Management
- Identify Risks
- Perform Qualitative Risk Analysis (Correct answer)
- Perform Quantitative Risk Analysis
Correct answer: Perform Qualitative Risk Analysis
Perform Qualitative Risk Analysis uses the probability and impact matrix to categorize risks as high, medium, or low priority.
Question 3: A project manager is using a decision tree to evaluate two alternative courses of action based on risk probabilities. This technique belongs to which process?
- Identify Risks
- Perform Qualitative Risk Analysis
- Plan Risk Responses
- Perform Quantitative Risk Analysis (Correct answer)
Correct answer: Perform Quantitative Risk Analysis
Decision tree analysis is a quantitative technique used in Perform Quantitative Risk Analysis to compare options under uncertainty.
Question 4: Which risk response strategy involves partnering with another organization to share both the opportunity and the resources needed to pursue it?
- Exploit
- Enhance
- Share (Correct answer)
- Accept
Correct answer: Share
Share allocates ownership of an opportunity to a third party who is best able to capture it, such as through a joint venture.
Question 5: The Risk Report, added in PMBOK 6th edition, differs from the Risk Register in that it primarily provides:
- A list of individual project risks
- Information on overall project risk exposure (Correct answer)
- Detailed risk response plans
- Risk trigger conditions
Correct answer: Information on overall project risk exposure
The Risk Report presents information on overall project risk exposure, including a summary of individual risk findings.
Question 6: A contingency reserve is set aside to address which type of risk?
- Unknown unknowns
- Known unknowns (Correct answer)
- Black swan events
- Management reserves cover these
Correct answer: Known unknowns
Contingency reserves address known unknowns—identified risks with response plans that may still materialize.
Question 7: Which data representation technique in risk management plots risks on a two-dimensional grid showing probability on one axis and impact on the other?
- Tornado diagram
- Probability and impact matrix (Correct answer)
- Risk breakdown structure
- Hierarchical chart
Correct answer: Probability and impact matrix
The probability and impact matrix maps risks based on their likelihood of occurring and the magnitude of their effect on project objectives.
What is the Expected Monetary Value (EMV) of a risk with a 30% probability and a $50,000 negative impact?