Scope and WBS Development Flashcards
7 cards from real PMBOK practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Scope and WBS Development flashcards as text
A project team uses the 100% rule when building their WBS. This means:
Answer: The WBS captures 100% of the work defined in the scope and no more
The 100% rule requires that the WBS captures all work necessary to complete the project and includes no work outside the project scope.
A requirements traceability matrix links requirements to which of the following to ensure alignment throughout the project lifecycle?
Answer: Business needs, WBS deliverables, and test cases
The requirements traceability matrix links requirements from origin through business needs, deliverables, WBS components, and verification/validation activities.
Which input to the Define Scope process provides guidance on how scope will be defined, validated, and controlled?
Answer: Scope management plan
The scope management plan describes how the project scope will be defined, developed, monitored, controlled, and validated.
A project is constructing a hospital. The WBS includes 'Patient Ward' as a level-2 element. Level-3 elements include 'Electrical Systems' and 'Plumbing.' What decomposition approach is being used?
Answer: Deliverable-based decomposition by physical location
Decomposing by major deliverable or physical component (ward) into its subsystems (electrical, plumbing) is deliverable-based decomposition.
A project manager wants to collect requirements from 200 geographically dispersed stakeholders efficiently. The BEST technique is:
Answer: Questionnaires and surveys
Questionnaires and surveys are the most efficient method for gathering structured data from large, geographically dispersed groups.
What is the primary benefit of including a scope baseline in the project management plan?
Answer: It provides a fixed reference for measuring scope performance and managing changes
The scope baseline serves as the approved reference against which project scope execution is compared and change requests are evaluated.
During a project review, an auditor finds that team members are completing work NOT listed in the WBS. What PMBOK process should have prevented this?
Answer: Control Scope
Control Scope monitors project and product scope status and manages changes to the scope baseline, preventing unauthorized work.